ERC Refinery Project

±¹°¡: ´ëÇѹα¹
¹ßÁÖó: GS°Ç¼³(ÁÖ)
±â°£: 2013-10-07~2015-03-06
Note 1 : Pre-Engineering
(1) Evaluating GS E&C¡¯s Module split philosophy
(2) Suggest Module split philosophy in horizontal and vertical direction
(3) Preparing Module plan, Module list, and Module structural scheme
(4) Recommendation of load combination for In-place analysis if required
(5) Module design procedure between both engineering stages
Note 2 : Optimized Detail Engineering
(1) Inland -transportation analysis (Ro-Ro base transportation)
(2) Load in/Load out analysis
(3) Set down analysis for anchor bolt tightening on foundation
(4) Temporary support/loading frame design w/ pin type connection and connection design
(5) Weight control (including C.O.G calculation)
(6) Dimension control
(7) Lifting analysis if required
(8) MTO
(9) Performing 3D Modeling and clash check and coordination
Note 3 : Technical Support
(1) Fabrication Inspection at Shop
(2) Assessment of arranging SPMT by Transportation Company
(3) Design of Pre-assembled yard
(4) Preparing Constructability Plan
 
Note 4 : Construction Support (Optional)
(1) Re-split of Module and analysis
(2) Assisting weight control in case of changing module scheme
(3) Interface control with Transportation Company